Case study Data Center

Delivering Nearly 200 Computer Room Air Handlers on an Accelerated Schedule for a New U.S. Data Center

1 min read

Executive Summary

A European data center operator developing its first U.S. facility chose a lean delivery model, relying on individual original equipment manufacturers (OEMs) rather than a traditional general contractor. When the original supplier for the facility’s power room cooling significantly extended its lead time, the project schedule was at risk and the customer needed a new partner capable of moving quickly without compromising quality. 

  • 192 vertical up-flow CRAH units delivered for power room cooling at a new New Jersey data center.
  • 8–10 week lead time: first units shipped February 16, 2026, after a December 2025 PO, when the original supplier’s lead time slipped.
  • 26 shipments completed by July 20, 2026, keeping the project on schedule without a general contractor.
  • Full scope from one OEM: engineering design, application-specific refinements, manufacturing, delivery, on-site commissioning, and load bank testing.
  • Built for switchgear and UPS rooms, a high-heat, mission-critical space beyond the white space.

Download the full free case study below →